AI Data Centers Are Buying Used Jet Engines as New Power Turbines Take Six Years
AI data-center developers are hunting for used gas turbines and retired jet engines because ordering brand-new power equipment could leave their servers waiting for electricity until the next decade.
Some companies are buying refurbished machines, while others are converting aircraft-engine technology into generators that can run alongside their computing facilities.
New gas turbines now take an average of six years to deliver in the United States, according to energy consultancy Wood Mackenzie. Delivery discussions are already focused on 2030 and 2031, a timeline that clashes with an AI industry trying to bring enormous computing campuses online much sooner.
Global turbine orders have topped 100 gigawatts, compared with manufacturers' estimated annual capacity of just 60 to 70 gigawatts, Reuters reported. Siemens Energy, GE Vernova, and Mitsubishi Heavy Industries have all said orders are outpacing what they can produce.
Gas turbines can generate large amounts of electricity by burning natural gas to spin equipment connected to a generator. AI data centers need that power around the clock to run densely packed chips and cooling systems, and connecting new facilities to public electricity grids can itself take years.
The International Energy Agency expects global data-center electricity consumption to nearly double from 485 terawatt-hours in 2025 to 950 in 2030. Consumption at AI-focused facilities is projected to triple over the same period.
From airplane engines to AI power plants
One way around the backlog is an aeroderivative turbine, a power generator built using technology adapted from aircraft jet engines.
Other companies are going further by seeking older machines and retired aircraft engines that can be rebuilt for stationary power production. For example, AI infrastructure firm Crusoe ordered 13 units from Missouri-based ProEnergy in April, each rated at 50 megawatts, for a combined 650 megawatts. The jet-engine-derived equipment is intended for future U.S. data centers, but the contract doesn't mean that Crusoe bought engines removed from retired aircraft.
Second-hand machines can also carry a substantial discount. Used turbines in good condition sell for about $1.5 million to $1.7 million per megawatt, compared with roughly $2 million to $2.5 million for new units, according to equipment brokers and energy analysts interviewed by Reuters.
One broker described a sale of two smaller turbines totaling 29 megawatts for $12.5 million. Equivalent new equipment would have cost about $35 million and taken five years to arrive, he said.
"That secondary market is very, very hot right now," EthosEnergy CEO Ana Amicarella told Reuters, adding that asking prices are climbing as more buyers compete for the same machinery.
The problem with second-hand power
Building a power plant beside a data center also brings fuel needs, air emissions, and permits into the equation. The Environmental Protection Agency says stationary turbines and engines used by data centers are subject to federal air-pollution standards.
Last week, OpenAI promised to cover electricity and grid costs at future campuses it owns and operates after voters backed tighter restrictions on data-center construction.
Power-market research firm Cleanview identified about 90 gigawatts of proposed on-site generation at U.S. data centers in its mid-2026 analysis. Only about 2 gigawatts was operating at the time.
Developers are looking beyond turbines, too. Finnish manufacturer Wärtsilä told Reuters it had booked around 3 gigawatts of orders from U.S. data centers since spring 2025 for generators powered by gas engines rather than turbines.
-- Price
This content is provided for general informational purposes only and doesn't constitute financial, investment, legal, or tax advice. Any events, rewards, online promotions, or related information mentioned herein should not be considered a recommendation, solicitation, or invitation to purchase, sell, trade, or otherwise deal in any crypto assets. Crypto assets are highly volatile and may result in loss. The availability of WEEX services, products, and related events may vary by region. You are responsible for ensuring that your participation is in accordance with applicable local laws and regulations.
You may also like

Why Is It Difficult for Income Reflows to Boost Cryptocurrency Prices? Net Reflows Are Weakly Correlated with Prices

Murphy USA Emerges as Top Dividend Stock with 14-Bagger Growth

Should You Invest $1,000 in Bloom Energy Right Now?

Better Buy: Bitcoin vs. Ethereum

El Salvador Plans to Add Over 1 Gigawatt of Power Capacity to Support Bitcoin Mining

3 Data Center Power Stocks Down More Than a Third From Their Records to Buy Now and Hold Through 2030

Negotiations on Australia's Gas Reservation Proposal Continue, Legislation Hopes to Pass Next Week

BitMine Reports $10.1 Billion Loss, Nvidia May Set Record for Longest Consecutive Weekly Decline

Where Will Bloom Energy Stock Be in 5 Years After More Than Doubling Its Revenue in 2026?

As traditional giants rush into digital dollars, USDD’s Yvonne Chia explains why 24/7 access, self-custody, and transparent yield give decentralized stablecoins an edge banks can’t replicate.

Ethereum Delays Update Amid Massive Cost Surge

Chevron Exploration Vessel Arrives in Greece, Initiating Offshore Oil and Gas Exploration

When Accounts Become 'Programmable': The Trade-offs from EIP-7702, ERC-4337 to Native AA

Jera Considers IPO to Support AI-Driven Business Expansion

ChatGPT Wallet Partners with Visa: Does the Agent Economy Still Need Stablecoins?

Ethereum Glamsterdam Upgrade May Be Delayed Until May 2027

FERC Approves Five Energy Projects

FERC Approves Five Energy Projects

Fed: What if the American central bank makes a serious mistake?

MARA and Riot sold 60,845 Bitcoin. Where did the cash go?

Japanese E-commerce Nippon Chokuhan Trials Yen Stablecoin JPYC Payments

Dalian's Industrial Added Value Increased by 6.6% Year-on-Year from January to October

Who benefits from Sui’s staking rewards before all its tokens circulate?

News Flash: Inflation Is Reaccelerating, and There's More at Play Than Just Higher Gas and Diesel Prices

South Korea's Toss Introduces Cryptocurrency Wallet to 30 Million Users, Usable Without Exchange Accounts

Weichai Power's SOFC Business Steadily Advances Capacity Construction

IEA Warns: Carbon Emissions from Data Centers Will Increase by 70% by 2030

EU Delays Implementation of Methane Emission Regulations for Fossil Fuel Imports

International Energy Agency: Energy Market Can Operate Independently of the Strait of Hormuz